President William Ruto says the government has set aside about KSh 5 billion to extend the Standard Gauge Railway (SGR) from Voi through Taita Taveta into Tanzania, to move passengers and cargo and deepen cross-border trade.

He spoke on Sunday, 27 September 2026, at a service in Mwatate.
“We are already extending SGR from Naivasha to Kisumu and to the Malaba border. As we extend that, it is also important to link Voi and Tanzania. We’ve already set aside around KSh 5 billion for that project,” he said.
That is a funding set-aside and a political commitment, not a finished railway. Design, full cost, contractor, groundbreaking date and a clear Kenya–Tanzania technical deal were not published with the speech.
Where the Line Would Run
Ruto said the line would start from the SGR corridor at Voi, run through Taita Taveta and then cross into Tanzania. Stations he named:
- Mwatate
- Bura
- Mwakitau
- Taveta
“You will be able to drop passengers here and carry cargo,” he told the congregation, arguing that Taita Taveta should not be left out of national infrastructure plans.
Mobile: Swipe left / right → ←
| Item | What was announced |
|---|---|
| Money cited | About KSh 5 billion set aside |
| Branch point | Voi (from the main SGR corridor) |
| Stations named | Mwatate, Bura, Mwakitau, Taveta |
| End goal | Link into Tanzania |
| Use case | Passengers and cargo |
| Status | Announcement and early planning |
← Swipe on mobile →
Do Not Mix This With the Old Voi–Taveta Line
Two different projects now sit on the same general corridor.
1. Metre-gauge rehabilitation (already launched)
In April 2026, Ruto launched work on the historic Voi–Mwatate–Taveta metre-gauge railway (MGR). The government put that job at about KSh 5.5 billion, with a dry port planned for Voi. The line is about 130 kilometres. It had been largely idle for years. In July 2026, Kenya Railways said about 70 percent of earthworks were complete.
2. Standard-gauge extension (new announcement)
The September speech is about a new SGR-standard link from Voi towards Tanzania. Same region, different technology and a different budget line. The MGR is the near-term rebuild. The SGR branch is the longer-term, higher-capacity idea.
Mobile: Swipe left / right → ←
| Project | Gauge | Money cited | Where it stands |
|---|---|---|---|
| Voi–Tanzania SGR | Standard gauge | About KSh 5bn set aside | Announced 27 Sept 2026; not yet a works programme |
| Voi–Mwatate–Taveta MGR | Metre gauge | About KSh 5.5bn | Launched April 2026; earthworks advanced by mid-2026 |
| Naivasha–Kisumu–Malaba SGR | Standard gauge | Separate national project | Main western build towards Uganda |
← Swipe on mobile →
How It Fits the National Rail Push
Ruto tied the southern idea to the western SGR push from Naivasha through Kisumu to Malaba. That corridor is the current priority for transit cargo into Uganda and the Great Lakes. Reporting on that western package often describes a combined Naivasha–Kisumu–Malaba length of about 475 kilometres.
A working Voi–Tanzania SGR branch would give Kenya a second standard-gauge border option, this time south. For that to matter commercially, both sides need matching infrastructure, border procedures and a real freight case, not only a speech in Mwatate.
Treat the KSh 5 billion figure carefully. Ruto said money has been “set aside.” He did not publish a full bill of quantities. A complete SGR spur usually costs more once track, stations, signalling and border works are fully scoped. The next proof points are a budget line, feasibility work and any formal cross-border agreement.
What Happens Next
- Watch for Treasury and Kenya Railways papers that turn “around KSh 5 billion” into a defined project.
- Follow the MGR rebuild on Voi–Taveta: that is the corridor work already moving on the ground.
- Track western SGR progress to Malaba: still the main national construction focus.
- Any real link into Tanzania needs bilateral engineering and operations details, not only Kenyan station names.
On the same Taita Taveta visit, Ruto also spoke about title deeds and other local projects. Those pledges sit outside the rail engineering story.
Read also:Ruto Calls on Banks to Lower Loan Rates From 14.39% Average
Bottom Line
On 27 September 2026, President Ruto said Kenya has set aside about KSh 5 billion to extend the SGR from Voi through Mwatate, Bura, Mwakitau and Taveta into Tanzania. The aim is passengers, cargo and regional trade. That plan is separate from the KSh 5.5 billion metre-gauge revival already under way on the same corridor.
The western SGR to Malaba remains the big active build. Until design, full costing and cross-border arrangements land in public documents, the southern SGR link is a funded intention, not a train you can board.
Sources:
People Daily – Ruto announces KSh 5B SGR extension to Tanzania;
The Star – Sh5bn plan to extend SGR to Tanzania border;
The Eastleigh Voice – Ruto promises Sh5 billion SGR extension;
Citizen Digital – Ruto reveals plan to extend SGR into Tanzania;
Sauce.co.ke – Sh5 billion Voi–Tanzania SGR plan;
People Daily – Kenya Railways Voi–Taveta MGR update (July 2026).
This article is for information only. Costs, routes, timelines and cross-border links may change as studies and agreements advance.
